U.S. Data Center and IT Investment
U.S. Data Center and IT Investment
Experts expect U.S. data center building to more than double its 2025 level by 2035.
Hover to highlight a group, click to show or hide itTap a group to show or hide it
Our Analysis
How do we interpret these results
Forecasts are indexed so that 100 equals 2025 investment in data center structures, a base of $40.8 billion. All three groups expect rapid growth by 2026, continuing through 2028, when experts give the highest median forecast at 176, followed by superforecasters at 170 and the public at 148. Investment keeps rising through 2035, but at a slower annual rate, and superforecasters overtake experts to give the highest median, at 250. Superforecasters are the most uncertain group at that horizon: their median 10th and 90th percentile forecasts for 2035 span 132 to 400. At every horizon, experts' and superforecasters' median forecasts are statistically indistinguishable, while the public is significantly lower at the 50th percentile throughout.
Forecasts by group
Median forecasts from each group
| group | 2026 | 2028 | 2035 |
|---|---|---|---|
| Experts | 128.6 | 176.3 | 220 |
| Superforecasters | 130 | 170 | 250 |
| Public | 120 | 148.3 | 184 |
Click any cell to compareTap any cell to compare
* Denotes non-overlapping bootstrapped confidence intervals between group aggregates.
Rationale analysis
The main lines of reasoning driving the spread in estimates
AI buildout sustainability
A central cross-category consideration is whether current spending on the AI buildout is sustainable. High-investment respondents typically conclude that it is: “I now think most of this investment is backed by real, growing demand rather than hype: demand looks like it's outrunning supply, with power and grid connections the main bottleneck rather than any lack of appetite. So I expect the buildout to keep climbing.”; “Enterprises have barely begun moving substantial production workloads into persistent AI systems.” Low-investment respondents often express skepticism: “In all cases there is an overcapacity possibility that would need to be accounted for.”; “The historical trend line is unsustainable.”
Offshoring
Several respondents note a buildout that migrates offshore wouldn’t be captured by a measure of US private investment. As one writes, “China’s push toward domestic chip supply chains decoupled from the HBM[high bandwidth memory]/memory crunch, plus Gulf-state sovereign buildouts, means a growing share of new AI infrastructure investment increasingly lands outside the US NIPA [national income and product] accounts entirely—this doesn't shrink global AI capex, but it directly caps the US-specific structures and equipment lines [this] question asks about.” Another respondent notes that “nationalization moves spend out of private accounts,” as well.
AI’s limited impact
Many low-investment respondents stress that this category (along with the information technology equipment category below) is economy-wide: “Data centers are under 5% of [electrical and communication structures]’s level—the key fact about [this] category, since it makes [it] insensitive to a data center boom.”; “Even a dramatic AI-driven surge arrives diluted.” High-investment respondents tend to acknowledge this factor, but emphasize that the scale of new load is large enough to show up regardless: “The more data centers that are actually completed, the more obvious it becomes that generation, transmission, distribution, substations, fiber routes, and communications infrastructure need to be rebuilt around a load-growth regime that the United States has not experienced for decades.” Other high-investment respondents point to factors unrelated to AI: “The electrical grid is in desperate need not only for data centers, but also electric cars and tools. As climate change gets worse, there may be more of a push…to move away from gas power to electricity.”
The flat history
Low-investment respondents often note that the real level of investment has barely moved in recent years: “[It] has been flat for five years despite constant talk of grid investment.”; “Fifteen years essentially flat, through the shale revolution, the renewables boom, and the first years of the AI surge.” Several high-investment respondents read the same flatness as having led to a backlog that will lead to a spike in investment in the years to come: “My 2028 figure has the bottleneck forcing real acceleration, and by 2035 I expect a construction boom of a scale not seen since the 1970s.”
Bureaucracy and regulation
Some low-investment forecasters argue that utilities will struggle to expand quickly and overcome supply chain constraints given that “utilities are slow companies and permitting/construction is slow even if there is demand.” One adds that investment in this domain “is prohibitively expensive, politically tricky for governments to fund, and presents all the same permitting, design, construction labor, and other costs that create bottlenecks for the data centers.” High-investment respondents tend to acknowledge this element, but believe demand—along with “money, political influence, and geopolitical expediency”—will “force the issue toward the end of the decade.”
The replacement cycle
High-investment respondents often cite the short life of hardware as a key reason investment in this sector will remain robust: “Structures [like data centers] last twenty-five years and servers last three or four. So once the installed base is large, replacement demand drives the equipment number even when construction stops growing.”; “Even if the growth of data centers slows, there will still be a demand for replacement of these systems.” Low-investment respondents don’t dispute that hardware has an existing shelf life, but instead point to reasons why this factor might not be enough. As one writes, “Open and smaller models could shift more inference onto existing or edge hardware, foreign supply constraints could limit quantities, and the late-2020s buildout could leave the economy digesting a mountain of underutilized equipment.”
Falling prices
Respondents from both poles broadly agree hardware is getting cheaper per unit of performance; low-investment respondents typically argue that this will suppress total investment. One notes, “Real dollar spending can stagnate even as unit compute rises sharply, since the [cost of compute]...historically falls,” and another that “prices and efficiency improvements offset some of the increase in real investment.” High-investment respondents instead tend to focus on recent confirmed growth rather than projections: “We have already seen unprecedented growth in computers, communication equipment, and other apparatus in 2025, a nearly one third jump driven by the server and GPU surge”; “BEA printed +45.9% annualized real growth in Q1 2026.”
Breadth of AI diffusion
Several high-investment respondents point to the likelihood that AI will diffuse broadly across the whole economy, and that as “AI becomes embedded throughout enterprise computing” it will begin “producing persistently higher equipment investment than before the AI boom.” One notes that we will also “have more robots interacting with the physical world and they will need IT support.” Low-investment respondents tend to emphasize factors like “memory/transformer scarcity” as reasons IT investment may remain muted, regardless of demand.
Rationale examples
High-quality rationales from forecasters across the range
Respondents
I see the three categories as one buildout moving at three different speeds. The equipment (c) is the demand itself (the chips and servers people are actually buying) and it’s growing fastest; it also keeps growing later on because hardware wears out and gets replaced every few years. The data-center shells (a) have to be built to house that equipment, so they follow, growing fast but from a small base. The grid and power structures (b) move slowest of all: they’re a huge, regulated, economy-wide category where even a strong buildout only nudges the total.
The largest…effect across all three categories is that the bottleneck migrates. In the early phase, advanced chips are scarce. Then packaging and memory become constrained. Then power availability becomes the problem. Then transformers, turbines, substations, fiber, cooling, water, and qualified construction labor become the problem. Then community opposition, permitting, and rate allocation become the problem. Solving each bottleneck does not end the buildout. It reveals the next bottleneck standing behind it holding a clipboard…
Respondents
A great deal of the construction that will be recorded in 2026 and 2027 is no longer an abstract aspiration delivered by a chief executive standing in front of a rendering of a tasteful glass building surrounded by trees that will absolutely not survive the construction process. Land has been acquired, utility agreements are being negotiated, equipment has been ordered, financing has been arranged, local town council meetings have ignored objections of residents concerned with the noise of fans and emergency diesel generators, and multiyear campuses are already moving through development.
The essence of this question is whether data center expansion will continue apace, plateau, or even reverse. I’m betting on continuing apace given the commercial and geopolitical advantages (whether real or perceived) to ‘winning’ the AI race. Google provides a recent example in that their projected AI capex, already high, keeps rising higher still. And the stated plans for capex spending on AI going into 2027 are enormous.
The current pace of AI capex spending looks unsustainable financially. Google, the hyperscaler with the biggest reserves, burned through $6bn in cash in Q2 2026 on AI infrastructure spending. For listed companies, as Google is now, and OpenAI and Anthropic will be soon, there’s a strong feedback loop here, investors won’t be mollified by speeches on long-term opportunities if earnings are impacted.
Respondents
[This] category is…boring and durable. It’s economy-wide power and telecom structures riding tailwinds that don’t care whether the AI trade works: grid modernization, electrification, a record utility-capex cycle…so this leg keeps grinding upward...
The near-term limitation is not demand. It is the speed at which electrical infrastructure can actually be planned and built. Data centers can be designed faster than transmission corridors can be permitted, substations can be interconnected, turbines can be delivered, and large transformers can be manufactured. Electricity demand is now expected to experience its strongest sustained growth in decades, with large computing facilities serving as a major driver, but translating that demand into measured annual structures investment requires utilities, regulators, landowners, equipment manufacturers, environmental reviewers, and approximately nineteen public authorities to agree that a wire may proceed from one place to another.
Respondents
A data center built in 2026 contributes to equipment demand when it opens. It contributes again when accelerators are refreshed, networking is upgraded, power systems are modified, storage expands, and the facility is retrofitted for hardware…By 2035, annual equipment investment can remain very high even if construction of entirely new shells has slowed because the country will be servicing and upgrading the enormous installed stock created during the prior decade.
Historical experience also suggests that investment in a transformative computing technology can grow rapidly for an extended period. U.S. business expenditures on computers and peripheral equipment rose at roughly double-digit annual rates for much of the period from 1980 to 2000 as computers spread throughout the economy.
This is a massive, economy-wide category. The explosive growth in AI hardware and GPUs will naturally get watered down by everyday IT spending, like standard PCs and servers.